Goal
Staging (Linode, n8n.pbs-staging.herbylab.dev, 139.144.16.8) is running an older generation of the PBS n8n workflows than the sandbox (n8n.pbs.herbylab.dev, box pbswp-test / 10.0.21.101). The intent was to push all sandbox work to Linode for real testing; that transfer never happened. This run moves the full current-gen set (21 workflows) onto staging, rebinds every credential to the staging values, brings the reply pipeline + hold/flush live (plumbing-verified, not live-post), and cleanly parks the stale old-gen so its credentials aren't lost.
Done = current-gen reply pipeline + hold/flush ACTIVE and plumbing-verified on staging; all other current-gen workflows imported inactive; stale old-gen renamed -bk and deactivated.
Locked Decisions
- Everything transfers — all 21 sandbox workflows, including the monitoring/observability stack.
- No wipe. Stale old-gen is renamed
<name>-bkand deactivated (renaming alone won't stop active triggers/webhook collisions). n8n credential objects are separate and untouched, so no creds are lost. - Credentials come from
/opt/backups/pbs-wp/staging.md. Imports rebind to the staging credential objects; sandbox cred values never land on staging. - Meta webhook path: set current-gen
insta-webhook-newto the same path the Meta subscription already points at (oldinsta-webhooko) so no FB-console change is needed. If it can't take that path → HALT + document. - Activation: reply pipeline (
Sub-instra-reply-handle-new,instra-reel-cache-new,insta-webhook-new,PostPBSUpdate_new,SendPBSChat_New, gchat) +PBS: Flush Held Comments/PBS: Held Comments TTL Sweep→ ACTIVE. Everything else (monitoring stack, duplicatePBS: Google Chat Notify) → INACTIVE. - Verification bar = plumbing (webhook GET handshake, credential resolution, node wiring, mock-payload run through the reply sub-workflow). No live IG posts — that's Travis's home-machine job.
- Hub DB already reconciled (confirmed this run: staging hub schema diff = 0 missing tables/columns,
held_commentspresent). No DB push needed for the hub. Monitoring-stack tables (metrics/auth/security) are NOT in the hub schema and are deferred with the inactive monitoring workflows.
Open Items
- Monitoring/observability stack has DB + host deps not present on staging → import inactive, build deps in a later run.
- Sandbox has a duplicate
PBS: Google Chat Notify (Sub-Workflow)(two IDs) — import the canonical one, park the other. - Sub-workflow (
executeWorkflow) references point at sandbox IDs → must be re-pointed to new staging IDs post-import. - Confirm
wordpress-installstaging-deploypinsgithub_repo_version: staging(carried from prior run).
Phases
- Export — pull all 21 current-gen workflows from sandbox n8n (read-only, via
docker exec n8n n8n export:workflow), stage JSON in/tmpscratch on herbys-dev. - Transform — per workflow: strip/rebind credential references to staging credential objects (values from staging.md); re-point
executeWorkflowsub-workflow IDs; normalize webhook path forinsta-webhook-new→ oldinsta-webhookopath. - Park stale — rename staging old-gen (
Sub-Instagram-Reply-Handler,Insta-Reel-Cache,insta-webhooko,PostPBSUpdate,SendPBSChat,sub-gchat) to<name>-bkand deactivate. Leave junk (My workflow 1/2/3, etc.) as-is unless it collides. - Import — push current-gen JSON into staging n8n; rebind credentials to staging objects; fix sub-workflow ID refs now that new IDs exist.
- Activate + verify — activate reply pipeline + hold/flush; webhook GET handshake; mock-payload run; credential resolution check. Everything else stays inactive.
- Report — thread checkpoint with final inventory (active/inactive/parked), any halts, and the live-test handoff for Travis.
Notes
- Sandbox n8n has no public API key stored; access is via SSH to
pbswp-test+docker exec n8n n8n ...CLI. Staging n8n has the API key in staging.md (JWT). - n8n exports do NOT carry credentials — imported workflows land with dangling credential refs that must be rebound to staging's credential objects by hand/script.
- Rollback is trivial: stale old-gen is renamed, not deleted; re-activating it + deactivating the new gen restores the prior state.
- Related threads:
pbs-staging-n8n-cutover(1003),pbs-staging-hub-deploy(1004),pbs-hold-and-flush(1002). - Run governed by
lovebug-unattendedskill, custom tier. Contract written to the run's Trellis thread.